Service Delivery KPIs
How quickly we inspect, connect and clear applications, month by month, against our 5-working-day target.
Customer response time is a cornerstone of our service delivery. To make sure customers are served consistently and efficiently, we monitor three key performance indicators every month, from January 2024:
- KPI insp: time from application to the first site visit (inspection)
- KPI p2mv: time from payment to connection on site
- KPI insp (AP): time to process CEB’s clearance for a Building & Land Use Permit (approval of plan)
KPI insp: New supply: application to first site visit
Expected service time: 5 working days.
4.4days on average
over the last 12 months
over the last 12 months
30/31months within the
5-day target
5-day target
Month by month (working days)
JanFebMarAprMayJunJulAugSepOctNovDec
2024755544333454
2025444454454445
20264455544–––––
Better than targetOn target (5 days)Above target
KPI p2mv: New supply: payment to connection on site
Expected service time: 5 working days.
4.8days on average
over the last 12 months
over the last 12 months
27/31months within the
5-day target
5-day target
Month by month (working days)
JanFebMarAprMayJunJulAugSepOctNovDec
2024646555554463
2025455565555544
20264555555–––––
Better than targetOn target (5 days)Above target
KPI insp (AP): CEB clearance for BLUP (approval of plan)
Expected service time: 5 working days.
2.7days on average
over the last 12 months
over the last 12 months
31/31months within the
5-day target
5-day target
Month by month (working days)
JanFebMarAprMayJunJulAugSepOctNovDec
2024433322232222
2025332222232333
20262233323–––––
Better than targetOn target (5 days)Above target
* The performance figures are the average number of working days taken to serve all such requests received in the month. In some exceptional circumstances the average may be slightly above the target service time.